In brief
Commissioning checks the installed combination of mechanics, drive and controls. Documented acceptance connects requirements to observable results.
Define test conditions first
Specify measurement location, load state, motion sequence and permissible deviation before the trial. An unloaded run can expose assembly defects but does not replace testing under representative load. Check rotation direction and mechanical clearance.
A hypothetical assembly axis should be tested with the intended workpiece variants. Positioning tasks require attention to settling and load changes as well as reaching the target. Record measurement equipment and its suitability in the plan.
Keep the handover traceable
The approved configuration includes component revisions, relevant parameters and instructions. Fault response, referencing and restart must suit the machine concept. Safety verification is a separate responsibility of the competent parties.
After a motor change or revised movement sequence, assess which previous evidence remains applicable. A successful earlier trial does not approve different loads. Include open points and responsibilities alongside results in the handover.
Information for technical discussions
- Requirement and measurable criterion
- Load variants and test sequence
- Configuration and parameter revision
- Results, open points and responsibilities